Procedures
GENERAL
PROCEDURES
Before
loading or discharging marine cargoes, the following information should
be obtained, recorded, and agreed upon to ensure that procedures to
determine the fullness condition are as thorough as possible:
-
The
capacity of the designated pipelines.
-
The
stated condition of the designated pipelines (full, slack, or empty).
-
The time
of last cargo movement through the designated pipeline(s).
-
The last
(or current) product in the designated pipeline(s).
-
The
temperature of cargo to be loaded or discharged.
-
The
sources of all the above information.
Agree on
the method of pipeline fullness verification to be used and on the
extent - if any - of corrective actions that may be required.
If
automatic equipment is used to record measurements, it must meet the
precision requirements described in API MPMS 3.1A and API MPMS 7.
Review
measurement accuracy limits outlined in API MPMS 3.1A, and agree on the
tolerance to be met for the method selected.
The
procedures described in API MPMS 3.1 A and API MPMS 17.2 for selecting,
calibrating, and using measurement equipment should be strictly
followed.
PROCEDURE
FOR INTERNAL CIRCULATION METHOD
Terminal
personnel should circulate product through the designated pipeline
system after the system has been isolated. Circulation should
pass through the designated dock manifold and be performed immediately
before and after custody transfer. If circulation cannot pass through
the designated dock manifold, then an evaluation should be made of the
validity and accuracy of using this method.
To apply
the internal circulation method, per- form the following steps
consecutively.
Step 1 -
Gauge the delivering and receiving tanks before line
circulation. Measurements should be taken using reliable
automatic gauging equipment or manual measurement equipment.
Step 2 -
Circulate sufficient product to displace at least 120 percent of the
capacity of the designated pipeline system. Close tank valves
and re-gauge tank(s) using the same method as that used for opening
gauges.
Step
3 - Using the tank calibration table, convert the measurements taken
before and after internal circulation to volumes. Total
Observed
Volume (TOV) should be used to quantify volumes transferred.
Step
4 - Compare measured volume delivered to measured volume received to
determine whether their difference exceeds the agreed
tolerance.
If the difference exceeds agreed tolerance, repeat line circulation and
the measurements. If the excessive difference persists, the
integrity of the system should be investigated.
Step 5 -
For purposes of line fill determination, the designated pipeline system
may be considered full if the difference between measured volume
delivered and measured volume received is within the agreed tolerance.
Note:
This does not necessarily ensure that voids do not exist in the line.
PROCEDURES
FOR LINE DISPLACEMENT METHOD
The
vessel should be on an even keel with no list. Otherwise, a
trim or list correction should be applied and noted on the
report. If a wedge calculation is necessary, refer to API
MPMS 17.1.
Note:
Even-keel measurements are preferred because of the precision
limitations involved in trim, list and wedge calculations.
The
vessel quantity survey should be conducted prior to line displacement.
The
number of vessel tanks used for line displacement should be minimized,
and their location should be selected to minimize changes in trim or
list.
Deck
lines, risers, bottom lines, and drop lines should be in the same fill
condition both before and after line displacement between vessel and
shore.
Agree on
the quantity to be displaced. TOV of product displaced should
be at least 120 percent of the combined capacity of all designated
vessel and shore transfer lines. (definition of TOV.)
Agree on
the cargo flow rate.
Line
fill differences should not be addressed independently of the overall
voyage analysis of the entire cargo transfer.
To apply
the line displacement method, perform the following steps consecutively
Step 1 -
Gauge and measure the temperature of delivering and receiving tanks
before line displacement. Measurements may be taken using
either automatic measurement equipment or manual measurement equipment.
Step
2 - Transfer the volume required for displacement between vessel and
shore. Re-gauge the vessel and shore tanks using the same
types
of equipment and technique that were used for the opening measurements.
Step
3 - Using shore and vessel tank calibration tables, convert the
measurements taken before and after line displacement to
volumes.
TOV should be used to quantify volumes transferred.
Step
4 - Compare measured volumes of delivering and receiving tank(s) to
determine whether their difference exceeds the agreed
tolerance.
If vessel and shore volumes differ by more than the agreed tolerance,
any or all of the following options may be exercised until all parties
agree that line fullness has been determined to their satisfaction:
-
Check
all calculations for accuracy.
-
Re-gauge
shore tank (or verify its meter reading) and re-gauge designated vessel
tank(s).
-
Re-gauge
all vessel tanks and reconfirm vessel line condition.
-
Repeat
the line displacement procedure.
-
Proceed
with cargo transfer and determine after transfer whether the line fill
difference has had any unacceptable effect on the cargo transfer
volume. The initial line displacement volume will normally be
part of the cargo transfer and must therefore be accounted for in the
total transferred quantity.
Step
5 - For purposes of line fill determination, the designated pipeline
system may be considered full if the difference between measured volume
delivered and measured volume received is within the agreed tolerance.
Note:
This does not necessarily ensure that voids do not exist in the line.
Sections of text taken from
API - MPMS Chapter 17 Marine Measurement
|