|  Note I: This method may not be 
						applicable to pipeline systems with extensive horizontal 
						sections since gases may remain in these sections.   Note 2: Should the high-point bleed-valve 
						method be selected, valves designated for this operation 
						should be identified.   Note 3: Product flowing through a 
						pipeline system while valves are being bled may cause 
						existing air pockets to move past the bleed point.  Sight-glass connections should be at the 
						top and bottom of the pipeline circumference and should 
						permit convenient visual observation.  If 
						sight-glass systems do not enable bleeding to evacuate 
						gases seen in the sight glass, one of the alternate 
						verification methods should be selected.  All appropriate valves between the 
						designated shore tank and the vessel berth should be 
						open and under sufficient positive pressure to permit 
						the line to be filled with liquid.  Appropriate action should be taken to 
						ensure that any venting of vapours or release of-liquids 
						during bleeding operations is safely controlled and 
						contained in accordance with applicable regulations.  The operation of high-point valves or 
						sight glasses should be performed by terminal personnel 
						and should be witnessed by authorized parties interested 
						in custody-transfer measurements.  To apply the high-point bleed-valve 
						method (or the sight-glass method), perform the 
						following steps consecutively.  
                           Step 1 - Before opening high-point bleed 
						  valves, ensure that lines are under positive pressure 
						  at bleed positions.   Step 2 - Place an appropriate container 
						  under each valve opening to receive liquid.   Step 3 - Slowly open the valve and allow 
						  it to remain open until liquid appears in a steady 
						  stream.   Note: Allow adequate time between the 
						  bleedings of any two valves for gas to collect at the 
						  bleed points.   Step 4 - Close the valve and proceed to 
						  the next bleed valve.   Step 5 - Bleed each valve in the same 
						  manner until all valves are bled.   PROCEDURES FOR PIGGING METHOD  The pigging method is an acceptable 
						method only when the terminal is fitted with the 
						launching and retrieving systems designed for this 
						purpose.  In the pigging method, a tight-fitting 
						wiping device (or "pig") is placed in a launching system 
						and then pushed through the designated pipeline system 
						with liquid, gas, or air.  The original contents of 
						the pipeline system are therefore completely displaced 
						by the air, gas, or liquid used to propel the pig 
						through the line.  All pigs should be accounted for after 
						use.  The operation should be repeated when pigs 
						are lost or damaged in pipelines.  The pigging method may be executed 
						before, after, or both before and after a cargo 
						transfer.  If the pigging method is executed only 
						before a transfer, the volume of the pipeline must be 
						added to the cargo transfer volume.  PROCEDURE FOR LINE PRESS METHOD (OR LINE 
						PACK METHOD)  This procedure assumes that the 
						designated pipeline system is tight and able to 
						withstand pressures applied during line press operations 
						without loss of line pressure as determined by pressure 
						readings from a calibrated pressure gauge.  This 
						procedure is invalid with any pipeline system that does 
						not meet this tightness recommendation. 
                          To apply the line press method (or the 
						line pack method), perform the following steps 
						consecutively. 
                           Step 1 - Close the valve at the dock 
						  manifold.  Open the shore tank and pump valves, 
						  and gauge the tank before line press.  
						  Measurements may be taken using either reliable 
						  automatic gauging equipment or manual measurement 
						  equipment.    Step 2 - Start the pump and run it until 
						  the discharge pressure stabilizes and/or reaches a 
						  predetermined pressure.  The predetermined 
						  pressure should be higher than the maximum static 
						  pressure available on the system.    Step 3 - Isolate the pipeline to prevent 
						  backflow and stop the pump. 
                            Step 4 - Once the pump has been shut 
						  down. record the pressure and re-gauge the tank using 
						  the same gauging method as that used for the opening 
						  measurements.  Record the tank product level.    Step 5 - If the tank product levels 
						  before and after the line press are within 1/8th 
						  inch (3 millimeters) of one another, pipelines may be 
						  considered liquid-full and no correction is necessary.  Step 6 - If the tank liquid levels before 
						  and after the line press differ from one another by 
						  more than 1/8th
						  inch (3 millimeters), relieve the line pressure into 
						  the tank until the pressure at the highest elevation 
						  is slightly above product vapour pressure and then 
						  repeat the test.  If the tank product levels 
						  before and after the second line press differ from one 
						  another by less than 1/8th inch (3 
						  millimeters), pipelines are now full of liquid because 
						  condensible vapours have been re-liquified and no 
						  further correction is necessary.    Step 7 - If the tank liquid levels before 
						  and after the second line press differ from one 
						  another by more than 1/8th inch (3 
						  millimeters), either the line fill condition may be 
						  corrected by one of the alternate methods listed 
						  earlier or - with the agreement of all parties - gas 
						  volumes may be estimated by procedures and 
						  calculations outlined in the Appendix.    Step 8 - For purposes of line fill 
						  verification, the designated pipeline system may be 
						  considered full if the difference between the volume 
						  gauged before line press and the volume gauged after 
						  line press is within measurement precision.    Note: This does not ensure that voids 
						equal to compressed gas volumes less than measurement 
						precision do not exist in the line.    LINE VERIFICATION AFTER CARGO TRANSFER  After cargo has been transferred, the 
						fullness condition of shore pipelines should be 
						determined by the application of any method outlined 
						earlier other than the line displacement method.  Establishing Agreed Tolerances 
                          The three methods that require 
						calculation of the line fill condition are 
                         
                          
                             the line displacement method,
                             the inter- nal circulation method, and 
                            
                             the line press method (or line pack 
							method).  With each of the three methods, two 
						measurements of the contents of each tank used are 
						taken: one measurement is taken before liquid is pumped 
						through or pressured in the designated pipeline system, 
						and one is taken after. 
                          Note: The precision of the measurement 
						for each tank-regardless of whether it's a vessel lank 
						or a shore tank -is  1/8th
						inch (3 millimeters). To agree on tolerances applicable 
						to comparing volumes between opening and closing 
						procedures, both the measurement precision limits above 
						and the historical vessel-to-shore line displacement, 
						internal circulation, or line press experiences should 
						be considered.  The factors listed under General 
						Procedures should be considered as possible influences 
						on measurement tolerances.  Special situations such 
						as those involving temperature variations between line 
						contents and tanks, the effect of volumetric shrinkage, 
						and product quality differences should also be 
						considered 
                           APPENDIX-LINE PRESS (OR LINE PACK) COMPUTATION    1. 
                        General  1.1 With the agreement of all parties, 
						the following procedures may be used when a second line 
						press, as outlined earlier, has resulted in a change in 
						tank liquid level of more than 1/8th
						inch (3 millimeters).  The purpose of the 
						calculation is to estimate the additional liquid volume 
						equivalent to those trapped gases that might not have 
						been condensed or re-liquified during the first of the 
						two line press procedures.  1.2 
                        Calculating the volume of gas coexisting with liquid after a line 
						press yields an estimate of the gas volume when methods 
						that would displace or remove trapped gases are 
						undesirable or impractical.  The calculation is 
						based on accepted physical ideal gas laws and is subject 
						to certain assumptions and limitations, which are listed 
						in '2'.    2. 
                        Assumptions and Limitations 
                          2.1 This procedure assumes that the 
						designated pipeline system is tight and able to 
						withstand pressures applied during line press operations 
						without loss of line pressure as determined by readings 
						from a calibrated pressure instrument.  This 
						procedure is invalid with any pipeline system that does 
						not meet this tightness requirement. 
                          2.2
						Calculations in this procedure assume that the pressures 
						observed and used are representative of pressures 
						occurring within a gas bubble inside a partially filled 
						pipeline.  Therefore, accuracy will be affected by 
						liquid hydrostatic head pressure (if any) between the 
						high point on the pipeline and the point of pressure 
						readings.  If pipeline elevation varies by a 
						significant amount, then either the pressure instrument 
						should be installed at the highest possible elevation 
						point on the designated pipeline system or a hydrostatic 
						head pressure correction should be applied.    Note: If the pressure gauge location is 
						lower than the highest point on the pipeline system. a 
						correction for hydrostatic head should be added to the 
						required vapor pressure.  The calculation for this 
						correction is as follows in English units:    
                          2.3 The effects of heat of compression on 
						the gas bubble(s) remaining after the line press need 
						not be considered because of the impracticality of 
						determining the temperature of trapped gases and the 
						relative complexity of calculation.  These effects 
						are minimized by the low mass (weight) of air relative 
						to that of the liquid (in the range from 50: 1 to 200: 
						I), the rapid air-to-steel heat transfer, and the fact 
						that a single compression stroke is per- formed.  
						The effect is further minimized if sufficient time is 
						allowed after compression or until pressure stabilizes 
						to permit heat equalization with the pipe walls. Several 
						minutes (or possibly longer in large diameter pipes) 
						should be sufficient time.    3. Calculations    The volume of the gas coexisting with 
						liquid in a designated pipeline system may be calculated 
						using data collected during line press operations as 
						indicated in the following equations:  
                          4. 
                        An Example   The following example uses Equations 2. 
						and 3 to calculate the shore tank-total observed volume 
						corrected for gas in liquid line:   
                          Sections of text taken from API - MPMS Chapter 17 Marine 
						Measurement |